CleanSpark Swings to Profit on Bitcoin Mark-to-Market Gain, Pivots to $6.6B AI Lease
CleanSpark reported a swing to net income in its fiscal fourth quarter, but the headline for investors was the company's rapid transformation into an AI data center developer โ and the deliberate pause on its next phase of leases in Texas.
The company posted net income of $9.8 million for the quarter ended September 30, reversing a $240 million net loss in the prior quarter. The swing was driven almost entirely by a $345 million non-cash mark-to-market gain on its Bitcoin holdings, compared with a $133 million charge in Q3.
Revenue fell 12% sequentially to $121 million, as an 11% drop in Bitcoin mined offset a modest increase in the average Bitcoin price. CleanSpark mined roughly 1,700 Bitcoin at an average price of $71,000, down from 1,900 in Q3. Gross margin compressed to 34% from 38%, as power costs rose 11% to $0.059 per kilowatt-hour due to seasonal warmer weather.
For the full fiscal year, revenue fell 25% to $577 million from $766 million, and the company posted a net loss of $987 million, including a $177 million non-cash impairment tied to the Sandersville transition from Bitcoin mining to data center operations.
The Sandersville Anchor
The most consequential development of the year came in July, when CleanSpark signed its first 20-year triple-net lease at its Sandersville, Georgia, site with a high-investment-grade tenant. The deal represents approximately $6.6 billion in contracted revenue and $330 million in average annual net operating income. Extension options of up to 11 years could lift contracted revenue to roughly $12.2 billion.
In September, the company closed a $2.3 billion non-recourse project-level bond offering at 7.875% due 2031. The deal was more than four times oversubscribed, with over $10 billion in demand, and carried a 92% loan-to-cost ratio. CleanSpark's parent equity contribution was less than $100 million.
"We are on time and on budget to deliver the first data hall in the fourth quarter of calendar 2027," CEO Matt Schultz said on the call. "Fiscal 2026 was a deliberate plan executed, and it taught us what the market is now learning. In data centers, sequence matters."
CFO Gary Vecchiarelli emphasized the risk-management approach behind the financing. "We reached 100% basis of design alignment between our tenant and EPCM prior to signing the lease," he said. "We also executed on a fixed fee, lump sum, turnkey contract with our EPCM that materially reduces our exposure to potential cost overruns."
Texas on Hold
While Sandersville represents a template, CleanSpark's next acts in Texas are stalled. The exclusivity period for its Sealy campus (285 MW gross capacity) and Brazoria campus (300 MW initial, plus another 300 MW planned) expired without a signed lease.
Schultz attributed the lapse to Texas regulatory uncertainty following the governor's mandate to pause data center development and review the approval process. "Signing leases against that backdrop would not have been prudent, and prudence is the point," he said. "The benefit of the longer timeline is that the value of these sites continue to go up."
Management pointed to two near-term catalysts: an ERCOT meeting on December 10 and a PUCT hearing on December 17. Harry Sudock, the company's chief business officer, called these "the largest unblocking piece for commercialization to happen in Texas for the entire sector."
"These are still large-scale, complex negotiated agreements," Sudock added. "What you saw us do at Sandersville was really a very de-risked and properly sequenced transaction."
Analysts pressed on whether the expiration of exclusivity signals weakening demand. Schultz pushed back, noting that credit costs have changed substantially and the price of energized megawatts has risen. "We've had inquiries not only from our existing Sandersville tenant, but across a wide section of the hyperscale and neocloud community," he said.
Beyond the Hyperscale Campus
CleanSpark is also looking to monetize smaller assets. Harry Sudock said the company is evaluating approximately 600 MW spread across 30 smaller sites (10-50 MW) for modular data center deployments, targeting hyperscalers seeking rapid deployment within 150 miles of major cities.
"The timeline for deployment isn't measured in quarters or years. It's measured in high single-digit months," Schultz said, citing demand from hyperscalers issuing RFPs for 10-50 MW sites.
Separately, a preliminary load study with MEAG suggests the Washington, Georgia, site could expand from 86 MW to as much as 500 MW over several years. CleanSpark recently acquired approximately 500 acres to support a future campus there.
The company also hired Ginna Raahauge as SVP of AI Data Centers, bringing experience from World Wide Technology, AWS, and Cisco Systems.
Capital Discipline and Bitcoin as Dry Powder
CleanSpark ended the fiscal year with approximately $1.3 billion in liquidity: $200 million in unrestricted cash and $1.1 billion in Bitcoin, plus $310 million undrawn on a Bitcoin-backed credit line.
Vecchiarelli was adamant that equity issuance is not on the table. "We have incredible optionality with no need and zero appetite to issue equity or equity-linked products to achieve our current objectives," he said. A new shelf registration statement is a "routine filing" and should not be viewed as an indication of any planned equity transaction, he added.
Instead, the company views its Bitcoin holdings as a source of non-dilutive capital. "It is reasonable to expect that we will fund highly accretive acquisitions and development of projects by selling or borrowing against our Bitcoin," Vecchiarelli said. He noted that the digital asset management team generated $30 million in incremental cash returns through derivatives and spot sales in FY2026.
When asked about buying back stock given the depressed valuation, Vecchiarelli said capital would be better deployed into AI data centers and land and power acquisitions. "Even though the stock price is nowhere close to a respectable valuation in our minds, we think that there's highly accretive opportunities in the marketplace," he said.
Mining Fleet: Right-Sized and Efficient
CleanSpark deliberately reduced its mining fleet by 17% to 200,000 miners during the year, improving fleet efficiency by over 11% to 14.8 joules per terahash. Average hash rate at year-end was 36 EH/s, down from 42.6 EH/s in Q3.
Vecchiarelli said there is no material CapEx planned for fleet refresh. The company will continue to mine as long as it is profitable, and will unplug Sandersville miners in late 2027 as data halls come online.
"We'll be months off from the 2028 halving by then, and we don't expect there to be any significant value unless obviously hash price and Bitcoin price rips," he said.
What Analysts Wanted to Know
The Q&A session focused heavily on Texas permitting, the timeline for lease activity, and capital allocation. Brett Knoblauch of Cantor Fitzgerald asked whether the December regulatory events would be the final clearing event for lease signings. Sudock cautioned that while regulatory certainty is a first step, negotiated agreements still require careful sequencing and basis-of-design alignment.
Greg Lewis of BTIG asked about the Washington expansion timeline. Schultz said the site has greater value today because tenants favor a scaled approach with a path to certainty of grid-connected megawatts. "We like the idea of a land-and-expand, start the project with the energized electrons we currently have, and then grow with our tenant," he said.
On the financing market, Joseph Vafi of Canaccord Genuity asked about the ability to fund the sector's CapEx run rate into 2027. Vecchiarelli said demand for compute remains high and grid power is limited. "We see multiple paths to victory here," he said, emphasizing high-quality lease terms and high credit quality tenants.
As the call closed, Schultz returned to the theme of execution. "While 2026 proved to be a transformational year for CleanSpark, we are positioned to accomplish even more in the quarters and years ahead," he said.
For investors, the coming months will be defined by two dates in December, and then by whether CleanSpark can replicate the Sandersville playbook in Texas.
Once added, BigGo Finance appears first in Google Search Top Stories, so you get the broadest, most up-to-the-minute, and most comprehensive global financial news first.
![[CleanSpark Q4 2026 Earnings Call] CleanSpark Posts $9.8M Net Income as $6.6B Sandersville AI Lease Anchors Pivot, but Sealy and Brazoria Exclusivity Lapses](https://img.biggo.com/v29RNK4bF82bss8BgL--ScZNqnouGaFW0fTrf_kCQig/fit/1200/0/sm/0/aHR0cHM6Ly9pbWcuYmdvLm9uZS9uZXdzLWltYWdlL2Vhcm5pbmdzX2NhcmQvMjAyNi0xMS9VU19DTFNLXzIwMjYtMTEtMjRfMTc5NTU2MzU0MS53ZWJw.jpg)