- Q4 bitcoin mining revenue $120.9 million, down 46%; FY26 revenue $576.5 million, down 25% [1].
- Q4 net income $9.8 million ($0.04 per basic share); FY26 net loss $987.1 million ($3.74 per basic share) [1].
- Mined 7,253 bitcoin in FY26 and held 13,530 at Sept. 30, including collateral; liquidity about $1.3 billion [1].
- Sandersville, Georgia: 20-year, $6.6 billion triple-net lease, funded by $2.276 billion of 7.875% notes; first data hall planned for November 2027 [1].
CleanSpark (NASDAQ: CLSK) said after the market close on Tuesday, Nov. 24, that bitcoin mining revenue fell 46% to $120.9 million in its fiscal fourth quarter, ended Sept. 30, 2026, and 25% to $576.5 million for the full year [1]. The company earned $9.8 million, or $0.04 per basic share, in the quarter, but posted a net loss of $987.1 million, or $3.74 per basic share, for fiscal 2026 [1].
Adjusted EBITDA, a non-GAAP measure, was $345.4 million in the quarter, while the full year showed an adjusted EBITDA loss of $304.2 million [1]. The company, which now calls itself a data center developer, ended the year with about $1.3 billion of liquidity: about $204.8 million in cash and about $1,130.5 million in bitcoin, including pledged collateral [1].
The numbers
The quarter included a $305.6 million gain on the fair value of bitcoin and a $171.7 million impairment charge; for the full year the company booked a $281.6 million loss on the fair value of bitcoin and a $118.7 million loss on bitcoin collateral [1]. CleanSpark mined 7,253 bitcoin in fiscal 2026, down 8%, as average hashrate fell 21% to 36.0 EH/s, and fleet efficiency improved to 14.8 J/Th from 16.7 J/Th [1]. It held 13,530 bitcoin at year-end, including collateral, valued at $1.1 billion at Sept. 30 prices [1].
AI data center projects
At Sandersville, Georgia, CleanSpark has a 20-year, $6.6 billion triple-net lease with what it calls a high investment-grade tenant, and funded the build with $2.276 billion of 7.875% senior secured notes due 2031 [1]. It said it has all material permits, a lump-sum turnkey construction contract, and construction on track for a first data hall in November 2027 [1].
In Texas it acquired the Sealy (285 MW) and Brazoria (up to 600 MW) sites, and 585 MW received conditional Batch Zero baseload designation [1]. The company said exclusivity at Sealy and Brazoria expired "during a period of temporary regulatory uncertainty" and that it is marketing them to its Sandersville tenant and others [1]. At Washington, Georgia, it has 86 MW energized and is studying an increase to 500 MW, and bought 500 adjacent acres [1].
"Fiscal 2026 was a defining year for CleanSpark as we made significant progress in executing our strategic transformation," said Matt Schultz, chairman and chief executive [1]. The release gave no financial guidance [1]. The results come in a month when US spot bitcoin ETFs have seen record outflows.
Companies mentioned