- Hyperscale Data sold all of its bitcoin, about 211.6 BTC, on Nov. 6 for gross proceeds of about $16.0 million, and used part of it to repay convertible notes [1]
- It expects the 20 MW AI deployment at its Michigan data center to cost about $122.1 million, with about $74.8 million still to pay between November and March [1]
- Current liabilities of about $231.2 million exceeded current assets by about $128.1 million at Sept. 30, and cash was $17.3 million [1]
- Management says existing cash and available financing are not expected to cover the next 12 months, raising substantial doubt about its ability to continue as a going concern [1]
Hyperscale Data, a holding company that has been turning its Michigan bitcoin mining site into an AI data center, warned that it may not have enough cash to keep operating for the next year, in its quarterly report filed on Wednesday, Nov. 18 [1].
The company said its existing cash and presently available sources of liquidity "are not expected to be sufficient" to fund its operations, obligations and planned capital spending, including the Michigan data center, over the next 12 months, and that "these conditions and events raise substantial doubt about the Company's ability to continue as a going concern" [1].
The bitcoin is gone
On Nov. 6 the company sold all of its bitcoin, about 211.6 coins, for gross proceeds of about $16.0 million [1]. About 208.4 of those coins had been pledged as collateral for senior secured convertible notes, and Hyperscale Data used part of the proceeds to repay those notes in full, about $12.8 million of principal plus a $1.3 million prepayment premium [1].
It had already sold about 686 bitcoin in August for about $43.4 million to repay loans taken through the Morpho decentralized lending protocol [1]. At Sept. 30 it held about $1.0 million of unrestricted crypto assets and $17.5 million of restricted crypto assets [1].
The AI contract and its cost
The cash need comes from a master services agreement with an AI infrastructure customer for about 20 MW of critical power capacity in Michigan, with a first 10 MW phase targeted for December 2026 and the second by the end of March 2027 [1]. The company puts the total contract value at about $1.2 billion only if the customer exercises two five-year extension options and Hyperscale Data meets its obligations [1].
Hyperscale Data estimates the build-out at about $122.1 million, of which it had paid about $47.3 million through Oct. 31 [1]. It expects to pay the remaining $74.8 million in two steps: about $27.4 million in November and December and about $47.4 million in the first quarter of 2027 [1].
Balance sheet
Third-quarter revenue rose to $44.8 million from $24.3 million a year earlier [1]. The company raised about $47.9 million by selling about 110.3 million Class A shares under an at-the-market program through Sept. 30, and says it plans to fill the gap through equity, debt and other financing, which it says is not entirely within its control [1].
Companies mentioned
Further sources
This article was produced by MLQ.ai's AI newsroom and checked against primary sources such as company filings, official releases and court documents. Reports from a single outlet are attributed. Editor: Peter Foy. How we work · Spotted an error? Tell us.
More like this
The stories that matter, in one email. Free — unsubscribe anytime.